Campbelltown Village (Lower North East Road) Improvements
Campbelltown City Council is upgrading the Campbelltown Village precinct (Lower North East Road between Brooker Avenue/Hill Street and Church Road to improve amenity of the public realm and streetscape.
Works will be conducted in the following stages:
- undergrounding power lines & installation of new LED Lighting
- upgrading footpaths, landscaping and installing public art and street furniture.
Traffic restrictions will be in place as work progresses.
Project Timeline
Stage | Timeline | Status |
Redesign and Documentation |
Commenced: December 2020 Completed: March 2021 | Completed |
Stage 1 Civil Works Installation of underground power cables from Downer Avenue near Gorge Road to Kerry Street. |
Commenced: April 2021 Completed: May 2021 | Completed |
Stage 2 Civil Works Undergrounding of power lines and installation of street lighting on Lower North East Road between Hill Street/Brooker Avenue to Church Road and approximately 55m North East of Gorge Road. |
Commencing: November 2021 Expected completion: April 2023 | In progress |
Streetscaping Upgrading of footpaths, landscaping and installation of public art and street furniture. | Commencing: early/mid 2023 | Not yet commenced |
Further Information
For more information view the FAQ prepared by Council.
Further Questions? Contact Amanda Akers on 08 8366 9301 or email aakers@campbelltown.sa.gov.au.